100k linear metres in 1 shift 29-10-15

BHS Corrugator already exceeding expectations

Share

An incredible 100,000 linear m2 was produced off the newly installed BHS corrugator yesterday.

While commissioning continues, the new BHS corrugator is surpassing expectations. In fact Board24 remains well ahead of schedule on the commissioning curve.

The team actually produced over 100,000 linear m2 within three quarters of a shift. At this stage the additional board is considered a bonus while the final aspects of the machine commissioning continues.

The members of the production team include: Jordan Bridges, John Monkhouse, Dave Nutter, Mark Skehan, Roberto Maneti and Zac Jolly.

Steve Dutton (Team Leader) and Andy Bridges (Production Manager) have also been the drivers, along with Jos Giesbers (BHS Trainer).

more news